KAMALA D. HARRIS
Attorney General
State ofCalifornia
DEPARTMENT OF JUSTICE
Via U.S. and Electronic Mail
Amy E. Million
Community Development Department
City of Benicia
250 East L Street
Benicia, CA 94510
October 2, 2014
1300 I STREET, 15TH FLOOR
SACRAMENTO, CA 95814
Telephone: (916) 445~5077
E-Mail: Scott.Lichtig@doj.ca.gov
RE: Attorney General’s Comments on the Draft Environmental Impact Report for the
Valero Benicia Crude-By-RailProject
Dear Ms. Million:
Attorney General Kamala D. Harris submits the following comments on the Draft
Environmental Impact Report (DEIR) for the Valero Benicia Crude-By-Rail Project (Project).}
The Project proposes improvements to Valero’s Benicia Refinery (Refinery) that, if approved,
will allow Valero to receive and process up to 100 tank cars of crude oil by railway per day from
North American sources.
With this and other projects like it, California is faced with a dramatic increase in the
amount of highly-flammable crude oils proposed to be transported by rail throughout the State,
the result of a recent oil boom from North American sources, including the Bakken shale in
North Dakota and Canadian tar sands. According to the federal government, rail shipments of
certain crude feedstocks, including Bakken shale, represent an “imminent hazard,” such that a
“substantial likelihood that death, serious illness, severe personal injury, or a substantial
endangerment to health, property, or the environment may occur.” 2 Indeed, accidents involving
these trains have already resulted in catastrophic consequences, including one recent calamity
that killed 47 people, incinerated an entire downtown area, and is expected to require the
1}The Attorney General submits these comments pursuant to her independent power and duty to
protect the environment and natural resources of the State. See Cal. Const., art. V, § 13; Gov.
Code, §§ 12511, 12600-12612; D’Amico v. Ed. ofMedical Examiners (1974) 11 Cal.3d 1,1415.
This letter is not intended, and should not be construed, as an exhaustive discussion of the
DEIR’s compliance with the California Environmental Quality Act.
2 See U.S. Dept. of Transportation (DOT), Emergency Order: Petroleum Crude Oil.Railroad
Carriers, Docket No. DOT-OST-2014-0067 (May 7, 2014).
Page 2
expenditure of $400 million in taxpayer funds to remediate its disastrous environmental
impacts.3
In the face of this unprecedented risk, it is important that the infrastructure and facilities
transporting and processing these feedstocks are specifically designed to present minimal risk to
life, public and private property, and the environment. In particular, officials entrusted with
protecting public health and safety must ensure that the hazards from these projects are fully and
accurately assessed, and the identified risks are mitigated to the fullest extent possible by law.
Unfortunately, the DEIR for this Project fails to properly account for many of the·
Project’s potentially significant impacts pursuant to the California Environmental Quality Act
(CEQA). Specifically, the DEIR:
1. Underestimates the probability of an accidental release from the Project by considering
only a fraction of the rail miles travelled when calculating the risk of derailment, by
relying on a currently unenforceable assumption that newer, safer tank cars will be used,
by failing to adequately describe the potential consequences of an accident resulting in a
release of crude oil, and by improperly minimizing the risk to public safety from
increased rail-use;
2. Improperly asserts that the proper baseline for the Project’s impact on air emissions is
determined by the Refinery’s maximum permitted emissions;
3. Fails to analyze the impacts on air quality from the foreseeable change in the mix of
crude oils processed at the Refinery;
4. Ignores reasonably foreseeable Project impacts by impermissibly limiting the scope of
the affected environment analyzed to only the 69-milestretch from Benicia to Roseville;
5. Fails to consider the cumulative impacts on public safety and the environment from the
proliferation of crude-by-railprojects proposed in California; and
6. Employs an overly broad determination of trade secrets, which results in the
nondisclosure of the types of crude oil to be shipped by rail and refined onsite. As a
result, the DEIR fails to provide sufficient information for an adequate analysis of the
safety risks from transportation or the air quality impacts from refining the new crude.
These issues must be addressed and corrected before the City Council of Benicia takes action
pursuant to CEQA on the DEIR or the Project.
3 Fishell, “Quebec government seeking $400 luillion for Lac-Megantic rail disaster cleanup,”
Bangor Daily News (September 19,2014).
Page 3
Background
Crude-by-Rail in California
From 2012 to 2013, crude-by-rail in California increased from one million barrels
imported to 6.3 million barrels imported, a rise of 506%.4 This surge in the amount of crude-by-
rail imports is replacing crude oil previously transported by ship or pipeline. The trend shows no
sign of abatement, and the California Energy Commission projects that by 2016, the State will
import up to 150 million barrels of crude-by-rail.5
Crude feedstocks from North American sources such as the Bakken shale in North
Dakota and tar sands in Canada have only recently been introduced to refineries, made available
by a combination of new extraction techniques and higher energy prices. Bakken crude is unlike
other crude being produced or shipped in this country, and it presents an “imminent hazard”
because it is more ignitable and flammable and thus more· likely to cause large, potentially
catastrophic impacts from a train crash or derailment.6 On the other end of the spectrum, crude oil extracted from Canadian tar sands is a low-grade, high sulfur feedstock that is not as volatile as light crudes like Bakken but contains chemical properties that make it particularly damaging to the environment when spilled and/or burned.7
This dramatic increase in cnlde-by-rail represents a new potential hazard to public safety
and the environment in part because the crude oil is regularly transported by “high hazard
flammable trains” (HHFT), which are trains comprising 20 or more carloads of flammable
liquids such as crude oil.8 The DOT has determined that derailments of HHFTs will continue to
be more severe, “involve[ing] more cars than derailments of other types of trains” because
HHFTs are uniquely heavier and longer and therefore harder to control and less stable than other
rail traffic.9
4 Interagency Rail Safety Working Group, Oil by Rail Safety in California (June 10,2014) p.l.
5M . .
6 See Pipeline and Hazardous Materials Safety Administration, Dept. of Transportation,
Operation Safe Delivery Update (2014) p. 1. See also U.S. DOT Emergency Order, Petroleum
Crude Oil Railroad Carriers, DocketNo. DOT-OST-2014-0067 (May 7, 2014).
7 U.S. Dept. of Transportation, Draft Regulatory Impact Analysis, “Hazardous Materials:
Enhanced Tank Car Standards and Operational Controls for High-Hazard Flammable Trains;
Notice of Proposed Rulemaking.” July 2014 [Docket No. PHMSA-2012-0082] (HM-251), p.81.
8 DOT proposed regulations define a “high hazard flammable train” as a train comprised of 20 or
more carloads of Class Jflammable liquids such as crude oil. 79 Fed.Reg. 45017 (August 1,
2014).
9 U.S. Dept. of Transportation, Draft Regulatory Impact Analysis, “Hazardous Materials:
Enhanced Tank Car Standards and Operational Controls for High-Hazard Flammable Trains;
Notice of Proposed Rulemaking.” July 2014 [Docket No. PHMSA-2012-0082] (HM-251), p.24.
Page 4
This boom in crude oil being transported by rail has corresponded with a maj or increase ‘
in the number of accidents involving such trains. In 2013 alone, trains spilled 1.1 million gallons
of crude oil, a 72% increase over the total amount of oil spilled by rail in the nearly four previous
decades combined. 10 Since the beginning of2013, at least nine major accidents related to crude~
by-rail have occurred. Among the most notorious include:
•Lac Megantic” Quebec-On July 5, 2013, a train loaded with 72 tank cars of crude oil being transported from North Dakota to New Brunswick stopped on a track with a descending grade. The train later began rolling downhill toward the town of Lac-Megantic, about 30 miles from the U.S. border. Near the center of town, 63 tank cars derailed, resulting in multiple explosions and subsequent fires. The accident killed 47 people and destroyed substantial sections of the town, causing the evacuation of 2,000 people. It was later determined that the crude oil released was more volatile than the transporter had originally reported to Canadian authorities.
• Aliceville, Alabama-On November 8, 2013, a train hauling 90 cars of crude oil from
North Dakota to a refinery near Mobile derailed on a section of track through a wetland
near Aliceville. Thirty tank cars derailed and a dozen of these burned. The derailment
occurred on a shortline railroad’s track that had been inspected ,and cleared only a few
days earlier. The train was travelling under the speed limit for this track.
• Casselton, North Dakota-On December 30,2013, an eastbound BNSF Railway train
hauling 106 tank cars of crude oil struck a westbound train carrying grain that shortly
before had derailed onto the eastbound track. Some 34 cars from both trains derailed,
including 20 cars carrying crude, which exploded and burned for over 24 hours. About
1,400 residents of Casselton were evacuated.
• Lynchburg, Virginia-On April 30, 2014, 15 cars in a crude oil train derailed in
Lynchburg’s downtown area: Three cars caught fire, and some cars derailed into a river
along the tracks. The immediate area surrounding the derailment was evacuated.11
Crude-by-rail projects employing HHFTs continue to profligate in California, and
economic factors suggest that this trend will continue for the foreseeable future. This Project in
Benicia is but one’ of at least twelve other crude-by-rail related projects that are either already
10 Tate, “More oil spilled from trains in 2013 than in previous 4 decades, federal data show,”
McClatchyDC,(January 20, 2014).
11 Crude~by~rail accidents have also occurred in Philadelphia, PA, Vandergrift, PA, and LaSalle,
CO, in addition to the Canadian provinces of Alberta and New Brunswick. Congressional
Research Service, “U.S. Rail Transportation of Crude Oil: Background and Issues for Congress”
(May 5, 2014); Associated Press, “Colorado derailment: Six crude oil tankers jump track” (May
10,2014).
Page 5
operational or being considered in California. In addition to Benicia, crude-by-rail projects exist
in Richmond, Pittsburg,12 Martinez, Santa Maria, Stockton, Los Angeles, Bakersfield (two
projects), Wilmington (two projects), and Sacramento (two projects). 13 If approved, these
projects would cumulatively result in billions of gallons of crude oil being transported by HHFTs
annually throughout California.
The Valero.Benicia.Crude-by-Rail Project
Valero has applied to the City of Benicia for a Use Permit to construct improvements and
install equipment that would allow the existing Refinery to begin receiving and refining crude
feedstocks by rail, at a level of 100 tank cars daily. The crude-by-rail would be delivered in two,
50 car trains each day to the Refinery, totaling 70,000 barrels of North American crudes. The
cnlde-by-rail deliveries would purportedly replace crude oil feedstocks currently arriving by
ship. The significant components of the Project, as presented·in the DEIR, include construction
of offloading racks, rail spurs and new track, and additional supply piping from the rail spur to
the Refinery. (DEIR 3-5).
Comments on the DEIR
TheDEIR fails to adequately analyze the Project’s impacts to up-rail communities.
The DEIR en1ploys improper standards of significance, unenforceable mitigation
measures, and inadequate analyses to conclude that the Project will not have a significant impact
on “up-rail” communities, including those communities located between Roseville and Benicia
through which HHFTs will pass if the Project is approved. This analysis, broken up in the DEIR
into five subsections, is defective in the following areas:
(1) The probability of an accidental release of crude oil from a train
The DEIR employs a flawed quantitative analysis to conclude that the probability of an
accidental release of crude oil from a train is only one in 111 years. (DEIR App. F). First,
because the DEIR limits its analysis to only the 69 mile rail stretch from the Union Pacific
Railroad (“UPRR”) Roseville Terminal to Benicia, it severely underestimates the risk of an
accident related to the Project. The tank cars containing crude oil do not originate in Roseville,
they are delivered by rail from particular sources, including North Dakota and Canada. While
the precise route from these sources throughout North America to the Refinery may be somewhat
indeterminate, the potential rail routes from within the California borders to the Roseville
terminal are limited to a handful of options, and an assessment of these foreseeable impacts using
12 The’Attorney General submitted a CEQA comment letter on the Recirculated DEIR for the
WesPac Pittsburg Energy Infrastructure Project on January 15,2014.
13 Hays, Kristen, “Factbox – California crude slates and oil-by-rail projects,” Reuters (September
10,2014).
Page 6
reasonable assumptions of future crude oil sources should have been performed. This is
particularly true given that, despite claiming that the routes are too speculative to analyze for
purposes of public safety, the DEIR does, in fact, analyze these very routes in its discussion of
both air quality impacts (DEIR 4.1 ..22) and greenhouse gas emissions (GHG) (DEIR4.6-9).
Second, the DEIR’s risk analysis assumes that Valero will only transport crude oil in
newer model “1232” tank cars, which reduces the estimate of public health risks to up-rail
communities. These newer, presumptively safer tank cars, however, are not required by current
federal regulations. 14 The DEIR presents no evidence to support the assumption that only the
newer tank cars will be used, because Valero only makes a voluntary commitment to upgrade its
tank cars, a commitment that appears to be unenforceable as the Project is now proposed. Such
an unenforceable mitigation measure and/or condition of Project approval is a violation of
CEQA’s requirement that these commitments be “fully enforceable through permit conditions,
agreements, or other legally binding instruments.”15 The City of Benicia itself asserts that it is
preempted from enforcing Valero’s obligation to use the newer and safer rail cars and states that
it “must rely on the federal authorities to ensure that any such risks are mitigated as
appropriate.,,16 (DEIR 4.7-20). But, since DOT regulations currently allow use of DOT-Ill
14
49 C.F.R. 179. On August 1,2014, the DOT published a Notice of Proposed Rulemaking
seeking comments on new tank car standards for the transport of materials such as crude· oil and
ethanol. The proposed rules include a variety of options for phasing out the currently.;.used DOT-
111 tank cars in favor of safer tank cars such as the 1232 tank car, or other improved designs. It
is unclear when these new regulations might take effect, but the earliest proposal for the
elimination of DOT-Ill tank cars to transport crude oil is 2017, and oil corporations are
advocating for additional delay due to the increased costs associated with upgraded tank cars and
a shortage of supply of 1232 tank cars. See 79 Fed.Reg. 45016 (August 1,2014).
15 CEQA Guidelines, Cal. Code Regs., tit. 14, § 15126.4, subd. (a)(2).
16 We do not express an opinion regarding wheth~r Benicia’s legal analysis is correct. The
extent that federal law, including the Interstate Commerce Termination Act (ICCTA), preempts a
state or local jurisdiction’s ability to minimize impacts associated with rail transportation projects
has not been definitely determined by the courts. “The circuits appear generally, for example, to
find preemption of environmental regulations, or similar exercises of police powers relating to
public health and safety, onlywhen the state regulations are either discriminatory or unduly
burdensome.” Fayus Enters. v. BNSF Ry. (D.C. Cir. 2010) 602 F.3d 444,451. The Ninth
Circuit has most recently determined that, “Generally speaking, ICCTA does not preempt state or
local laws if they are laws of general applicability that do not unreasonably interfere with
interstate commerce.” Association ofAmerican Railroads v. South Coast Air Quality
Management Dist. (9th Cir. 2010) 622 F.3d 1094, 1097-1098. Nonetheless, California law on
rail preemption issues is currently in flux. See Town ofAtherton, et aI., v California High-Speed
Rail Authority (2014) 228 Cal.App.4th 314 (request for depublication filed September 22, 2014);
see also Friends ofEel River v. North Coast Railroad Railroad Authority, et aI., (September 29,
2014) First Appellate District, Case No. CIV1103605. Factors relevant to Benicia’s ability to
exercise its police powers to lessen the Project’s significant impacts would likely hinge upon,
(continued…)
Page 7
tank cars for these purposes, there is no reasonable expectation that DOT (or any entity other
than Benicia) would enforce Valero’s commitment to use the 1232 cars. Furthermore, the DEIR
provides no evidence that Valero has enough stock of the upgraded 1232 tank cars (a scarce
commodity) to completely avoid use of the older DOT-Ill legacy cars.17
Finally, the analysis is flawed because it only considers crude oil releases of over 100
gallons as significant, despite the potential for significant impacts due to a crude oil spill of less
than 100 gallons. (App. F-2). Given the volatility and flammability of the crude feedstocks to be
imported, combined with the potential ignition sources during a derailment, the DEIR’s decision
to ignore the impacts associated with a release of less than 100 gallons is unsupportable.
(2) The consequences ofa release
The DEIR’s analysis recognizes that serious, even catastrophic, consequences mayoccur
from a release (and conflagration) of crude oil during a train accident. Among the potential
inlpacts, the DEIR acknowledges that: (1) a release in any area could require a significant
. hazardous materials cleanup; (2) a release in an urban area that were to ignite and/or explode
could result in property damage and/or injury and/or loss of life; and (3) a release into the Suisun
Marsh could result in significant damage to biological resources. The costs borne by the
California taxpayer from such a calamity could be substantial, given the DOT’s recent
acknowledgment that the insurance policies currently carried by crude-by-rail transporters .are
typically insufficient to cover even a moderate crude-by-rail accident, much less a major disaster
involving significant releases. 18 Nevertheless, the DEIR declares these potential consequences to
be insignificant under the flawed, quantitative risk assessnlent discussed above.
Even if the risk analysis were supportable, the DEIR provides no explanation for why the
potential fora major catastrophe involving crude-by-rail, even once every 111 years, is an
insignificant impact. The DEIR, other than a brief mention, gives little consideration to the
potentially serious, even catastrophic, impacts that a release of highly volatile and .flammable
crude oil would have on communities and the environment. The DEIR also gives no
consideration to the public health and safety risks presented by the proximity of 27 schools
located within Yl mile of theUPRR rail line between Roseville and Benicia along which HHFTs
(. .. continued)
amongst other things: (1) whether any proposed condition unreasonably burdens rail
transportation, (2) whether the condition is one of general applicability, and (3) whether the
project proponent is a “rail carrier” subject to federal law.
7 Despite Benicia’s assertion that it ispreempted from enforcing such a mitigation measure,
nothing precludes Benicia and Valero from executing an agreement to convert Valero’s
voluntary cOlnmitment to one that is enforceable under CEQA. Should aenicia and Valero come
to such an agreement, the assumption of use of exclusively 1232 tank cars could become
supportable.
18 Wolfe, “DOT: Rail insurance inadequate for oil train accidents,” Politico Pro (August 6, 2014).
Page 8
will travel. (DEIR 4.7-23-24). The federal government has declared that the shipment of
Bakken crude represents an “imminent hazard” because it is unlike other materials being shipped
by rail. These particular high-risk characteristics must be considered to adequately support a
determination of no significant impact.
(3) The reduction in the risk of accidental releases from a marine vessel) based on the reduction
in marine trips that would be caused by the Project
The risks associated with a release of crude oil in the ocean are fundamentally different
than the risks associated with crude-by-rail travelling long distances through urban communities
and environmentally sensitive lands. Nevertheless, the DEIR gives qualitative “credit” from the
qecrease in ship miles travelled and uses that “credit” to lower the Project’s overall risk. Any
benefit to up-rail communities from a reduction in ship use 50to 100 miles away is tenuous at
best and can not reasonably be factored into the risk equation for the Project.
(4) The recent history of accidents involving DOT-lll tank cars carrying crude oil
The DEIR implies that since th’e majority of previous major accidents.involving crude-
by-rail involved DOT-111 tank cars, those accidents are comparatively of little significance
because Valero has committed to using only the newer, safer 1232 tank cars. (DEIR 4.7-19).
Setting aside the issue of the enforceability of this “commitment,” the DEIR provides no
evidence.to support a determination that these HHFT accidents would have been of a
substantially smaller scope had 1232 tank cars been used. In fact, as the DEIR recognizes, just a
few months ago, a 1232 tank car ruptured and released crude oil during an HHFT derailment at
low speeds in Lynchburg, Virginia. (DEIR 4.7-19). The safety benefit of using 1232 tank cars
for HHFTs is currently the subject of significant scientific and regulatory debate and should not
be given substantial consideration in a qualitative risk analysis.
(5) The regulatory requirements designed to prevent releases and/or mitigate the consequences
in the event of a release from trains
The DEIR unreasonably relies on both recently promulgated regulations as well as
speculative future regulatory changes as a significant factor for determining that the Project will
. cause no significant impact. The efficacy of new DOT regulations is yet to be determined, and
crude-by-rail accidents continlJe to occur. Furthermore, the DEIR’s determination of no
significance relies in part onfuture DOT HHFT tank car regulations possibly being “more
stringent” than even the 1232 tank car standards, an uncertain result given that the regulatory
changes are not final. 19 (DEIR 4.7-19). In short, future changes made by DOT to regulations for
19 The DOT regulatory proposals are the subject of extensive industry group interest. See
Vantuono, William C., “DOT crude oil NPRM: Will cooler heads prevail?” Railway Age
(August 7,2014) [During a recent crude-by-rail forum, one industry insider declared that he
believed, “the final draft of the [Notice of Proposed Rulemaking on High-Hazard Flammable
(continued .. .)
Page 9
crude-by-rail are speculative, and their potential effectiveness is currently the subject of
considerable disagreement amongst various stakeholders.
By.employing an incorrect baseline, the DEIRminimizes potential impacts to air quality.
Under CEQA, the project baseline against which project emissions are measured is
“normally” defined as the physical conditions of the environment as it exists at the time of
publication of the Notice of Preparation (“NOP”) of the project EIR or at the time the
environmental analysis commenced.2o Courts have held that an agency has discretion to select an alternative baseline, but only if its choice is supported by substantial evidence, such as when existing conditions are not representative of “generally existing” or “historic” conditions?1 Thus,except in limited circumstances, CEQA does not allow an existing facility to define the project baseline by what it could emit, only what it actually does emit. As the Supreme Court found in Communities for a Better Environment (CBE) v. South Coast Air Quality Management District (2010)48 Cal.4th 310,322, “[a]n approach using hypothetical allowable conditions as the baseline results in ‘illusory’ comparisons .that ‘can only mislead the public as to the reality of the impacts and subvert full consideration of the actual environmental impacts,’ a result at direct odds with CEQA’s intent,”22
Here, the DEIR concludes that the project will have no significant impact on air quality because, even if Refinery emissions were to increase under the Project, those increased emissions would not exceed the maximum emissions allowed under existing permit limits (or”maximum permitted emissions”). Rather than using a baseline describing “existing conditions,” Benicia incorrectly uses the maximum permitted emissions as the baseline, asserting that this is proper because Valero holds permits for the Refinery’s process equipment issued pursuant to a 2003 EIR for the Valero Improvement Project (VIP).23 (DEIR C.1-3).
(. .. continued)
Trains and DOT 111 tank cars] could be more friendly to shippers than the first proposal.”
Railway Age’s Editor-in-Chief stated that this assertion, “helped affirm our view that the final
version of the DOT’s safety rules may include some changes to the ones proposed on July 23.”]
20 See CEQAGuidelines, Cal. Code Regs., tit. 14, § 15125, subd. (a).
21 For example, in Fairview Neighbors v. County ofVentura (1999) 70 Cal.App. 4th 238, the court
approved a baseline that reflected maximum permitted use (“daily truck trips”), because there
was record of actual daily truck trips meeting and even exceeding what was allowed under the
current permit. The court reasoned that use of actual traffic counts wOllld be “misleading and
illusory.” Fairview Neighbors, supra, at p. 243.
22 CBE, supra, at p. 322, citing Environmental Planning Information Council v. County ofEl
Dorado (1982) 131 Cal.App.3d 350, 358.
23 The baseline actually used in the DEIR is unclear, since the DEIR alternatively claims that the
baseline is both maximum permitted operations and annual average emissions, depending on the
section. (DEIR 4.1-10-11). This comment addresses the DEIR’s assertion, made repeatedly on
(continued.. .)
Page 10
There is no evidence, however, that the Refinery has ever operated at maximum
permitted ’emissions levels since the VIP was completed, and Benicia does not attempt to justify
that the permitted capacity reflects existing physical conditions. Under well-established CEQA
case law, this approach to baseline emissions is improper.
Further, the DEIR’s discussion of the CBE decision mischaracterizes and misinterprets
the California Supreme Court’s holding. (DEIR C.1-2). The section to which Benicia cites
n1erely allows a projected maximum baseline for projects that were exempt from CEQA review
entirely either (l) as a modification of a previously analyzed project,24 or (2) as the continued
operation of an existing facility without significant expansion of use.25
Benicia has not, nor can it, claim that either of these two exemptions to CEQA apply
here. To the contrary, the Project gives Valero the ability to process a crude feedstock with
chemical properties never contemplated during previous project review that the Refinery, as
currently constructed, cannot readily access. (DEIR 1-1). As inCBE, this qualifies as a new
project subject to CEQA review for the first time. Similarly, Benicia cannot claim that the
Project constitutes the continued operation of an existing facility without significant expansion.
The 2003 VIP DEIR specifically excluded expansion of the refinery to use crude oil feedstocks
delivered by rail from the impact analysis of the project,26 Therefore, pursuant to the CBE
holding, withoutany substantial evidence to support use of a baseline constituting maximum
permitted emissions, the proper baseline froni which to compare air quality emissions is the
Refinery’s existing conditions.
The DEIR fails to adequately ap.alyze the potential air quality impacts from new crud~
feedstocks.
The DEIR fails to include supportable analysis that Refinery emissions will not increase
upon Project completion. Although acknowledging that the North American crude feedstocks
that could be delivered upon Project completion may be of higher gravity and sulfur content than
the crudes currently processed, the DEIR nevertheless asserts that the Project will not result in air·
quality impacts, based on the asslJmption that – through blending – the average API gravity and
sulfur levels of the crude slate that would be processed upon Project completion would remain
within the same range as the crude slate previously processed at the Refinery. (DEIR 3-24, 4.1-
(. .. continued)
DEIR 4.1-11 and in Attachments C.1 and C.2, that the proper baseline is maximum permitted
operations and not existing conditions.
24 CEQA Guidelines, Cal.Code Regs., tit. 14, § 15162.
25 CEQA Guidelines, Cal.Code Regs., tit. 14, § 15301.
26 See VIP DEIR 3-52 and 4.8-14. (“Transportation accidents related to railcar shipments of
volatile hydrocarbon liquids can result in fires or explosions. However, the VIP will not increase
the rail shipment of these materials.”)
Page 11
17). This conclusory assertion is not supported by substantial evidence or any analysis. Even if
the crude-by-rail processed by the Refinery is blended to the existing range of gravity and sulfur
content, studies show that certain North American crudes often contain’higher levels of other
pollution-causing chemicals that would persist at higher levels despite blending to meet existing
gravity and sulfur limits.27 The DEIR does not assess this possibility and its effects, nor does it
disclose the composition of the expected crude slate to allow proper public scrutiny. (DEIR 3-
14).
The project as defined in hee DEIR impermissibly limits the geographic scope and ignores
foreseeable, significant impacts that will occur beyond the project’s arbitrary boundaries.
By limiting the analysis to only the 69-mile rail section from the UPRR Roseville
Terminal to Benicia and excluding the thousand-plus mile rail trip from the crude SQurce to
Roseville, the DEIR violates CEQA by not analyzing the Project’s foreseeable impacts,
including impacts along hundreds of miles of track within California. In evaluating the
significance of a Project’s environmental effects, the lead agency must consider not only direct
physical changes, but also reasonably foreseeable indirect physical changes to the environment.
28 CEQA further defines “environment” as “the physical conditions that exist within the area that
will be affected by the proposed Proj ect. ,”29
The DEIR largely ignores the Project’s impacts up-rail from Roseville, claiming that
analyzing the potential impacts along these routes would be “speculative,” because future crude
oil feedstocks could originate from multiple North American sources. (DEIR 4.7-1). However,
it is a certainty, not speculation, that the Project will result in HHFTs traveling long distances
with the potential to create significant environmental impacts before reaching the Roseville
Terminal, and, pursuant to CEQA, an analysis of these potential impacts is necessary. While the
, particular routes may not yet be determined, there are a limited number of potential paths for
trains to travel by rail to the Refinery, and the DEIR elsewhere makes similar projections for the
purposes of studying air quality andGHG impacts, approximating that HHFTs will travel 195
miles from the California border to the Refinery. (DEIR 4.6-9). Instead of limiting the analysis
of impacts along these routes to only air quality impacts, the DEIR should have used
comparable estimates to analyze all of the Project’s potential impacts. By arbitrarily setting the
Project boundary at the UPRR Roseville Terminal, the DEIR fails to analyze reasonably
27 For example, tar sands bitumens contains 102 times more copper, 21 times more vanadium, 11
, times more sulfur, six times more nitrogen, 11 times more nickel, and 5 times more lead than
conventional heavy crude oil. These pollutants contribute to smog, soot, acid rain, and odors that
affect residents nearby. R.F. Meyer, E.D. Attanasi, and P.A. Freeman, “Heavy Oil and Natural
Bitumen Resources in Geological Basins of the World,” U.S. Geological Suryey Open-File
Report 2007-1084 (2007) p. 14, Table 1 (available at: http://pubs.usgs.gov/of/2007/l084/).
28 CEQA Guidelines, Cal. Code of Regs., tit. 14, § 15064, subd. (d).
29 Pub. Resources Code, § 21060.5.
Page 12
foreseeable impacts related to the transport of crude oil by HHFTs over those significant
distances.
The DEIR fails to consider foreseeable cumulative impacts and risks
The DEIR impermissibly narrows the scope of potential cumulative impacts analyzed.
Under CEQA, a DEIR first considers whether the combined effects from both the proposed
project and other projects would be cumulatively significant. If the answer is affirmative, the
DEIR must consider whether the proposed project’s incremental effects are cumulative
considerable?O Absent this analysis, piecemeal approval of multiple projects with related
impacts could lead to severe environmental harm.31
Despite the “imminent hazard” that the transport of certain crudes present and the
substantial proliferation of crude-by-rail projects throughout California, the DEIR relies on its
flawed analysis, discussed above, to determine that no significant cumulative impacts exist to up-
rail communities from an increased risk of crude-by~railaccidents. The DEIR further declares
that:.
[F]or the Project to make a cumulatively considerable contribution to the impact
of hazards, two or more events (from the Project and another cumulative project)
would have to occur at the same time and affect the same places. The likelihood
of such a cumulative accident event would be even smaller than the estimated low
probability of a Project-related accident and spill.” (DEIR 5-17).
This limited analysis of only a so-called “cumulative impact event” involving the Project and
“another cumulative project” ignores the entirety of the cumulative impacts caused by a large
rise in the number of HHFTs traveling through both highly populated and environmentally
sensitive areas and the corresponding increase in the risk of an accident. As the DEIR’s own
analysis demonstrates, the risk of a derailment and accident involving HHFTs escalates with a
corresponding increase in the number of miles travelled and the number of train cars on the
tracks. (DEIR App. F-3). Despite the substantial increase in both of these metrics, the DEIR
dismisses any cumulative impact as irrelevant unless it also directly involves a derailment from
one of the listed projects. But the potential cumulative impacts go far beyond these “cumulative
impact events,” to the combined higher safety risks from increases in other train cars (carrying
crude oil or not) and increases in truck crossings. For example, the 2013 crude-by-rail
derailment and fire in Casselton, ND, was caused when a train transporting grain derailed onto a
second track into the path of an HHFT, which had too little time to stop before crashing into the
grain train. 32 The possible impact of a similar accident is completely ignored in the DEIR’s
cumulative impacts analysis. Only by focusing exclusively on these “cumulative impact events”
30 CEQA Guidelines, Cal. Code Regs., tit. 14, § 15130, subd. (a).
31 San Joaquin Raptor/Wildlije Rescue Ctr. v. County ofStanislaus (1994) 27 Cal.AppAth 713,
720.
32 79 Fed.Reg. 45019 (August 1,2014).
Page 13
and not the larger cumulative increased risks to up-rail communities from a dramatic upsurge in
HHFTs and other train traffic does the DEIR determine that the Project will have no significant
cUlTIulative impacts.
The cumulative impacts analysis is also deficient because it fails to consider the severity
of the cumulative impacts, a necessary component of CEQA analysis.33 Here, the extraordinary
flammability and volatility of the crude oil feedstocks merits discussion given the serious,
potentially catastrophic, impacts related to an HHFT accident. As a result, there is no basis for
the DEIR’s conclusion that the project will not cause any significant cumulative impacts.
An ove,rly proad grant oftrade secret protection prevents adequate public review of potel1tial
significant impacts.
An overly broad grant of trade secret protection prevents adequate public review of potential significant impacts.
The DEIR frustrates the purpose of CEQA by not disclosing information regarding the
particular crude oil feedstocks expected to be delivered upon Project completion. Instead, the
DEIR classifies all information regarding the characteristics ofpast, present, andfuture crude oil
refined ansite as a “trade secret” exempt from disclosure under CEQA.34 This missing
information includes the weight, sulfur content, vapor pressure, and acidity of these crude oil
feedstocks, information critical for an adequate analysis of the Project’s hnpacts, particularly
with regard to public safety and air quality.
This broad grant of trade secret protection directly conflicts with recent 2014 decisions
by both the DOT and the California Governor’s Office of Emergency Services (OES) that
infonnation about the specific characteristics of crude oil currently traveling by rail are not
protected trade secrets and should be publicly released.35 Indeed, OES has published disclosures
of crude-by-rail shipments of Bakken crude oil by Burlington Northern Santa Fe Railroad
(BNSF) associated with a different project.36 This failure of transparency in the DEIR is
particularly improper given that, under the same DOT Emergency Order that cOlnpelled BNSF’s
disclosure, Valero must submit to OES the withheld information regarding the properties of
crude feedstocks imported by rail, and OES will then release into the public. Benicia’s
33 CEQA Guidelines, Cal. Code Regs., tit. 14, § 15130, subd. (b).
34 SeeDEIR 1-5 and Appendix D: Discussion of Confidential Business Information. Trade
secrets are exempt froln disclosure pursuant to CEQA. (Pub. ResourcesCode,§ 21160).
California law defines a “trade secret” in the Government Code. (See Gov’t Code, § 6254.7,
subd. (d).)
35 See OES website, “Public Records: Bakken Shipment Notices & Correspondence” (available
at: http://www.caloes.ca.gov/HazardousMaterials/Pages/Oil-By-Rail.aspx); see also Tate, “Norfolk
Southern sues to block disclosure of crude oil shipments,” Miami Herald (July 27, 2014).
36 Id.
Page 14
nondisclosure of this information deprives both the public and Benicia officials of the informed
decision making process that is the “heart” of CEQA.37
The DEIR’s public disclosure of the crude oil as simply “Alaskan North Slope (ANS)
look-alikes or sweeter” does not allow for an accurate public review of Benicia’s analysis
regarding the significance ofthe Project’s impacts. (DEIR 3-24). The undisclosed properties of
the Refinery’s projected crude feeqstocks are necessary to assess the volatility and flammability
of the particular types of crude-by-‘rail, crucial factors in any determination that nOt significant
impact exists. As the DEIR itself explicitly recognizes, “the consequences of a release of crude
oil for a rail tank car depend on the properties of the crude oiL .. ” (DEIR 4.7-13). In other words,
potential releases associated with transporting and storing crude will vary based on the crude’s
chen1ical composition, including the contaminants it contains, its sulfur content, and whether it is
blended with other chemicals. Nonetheless, and despite this acknowledgment, the DEIR
includes no information regarding the characteristics of the crude oil that could·be transported by
raillJpon Project approval, undermining CEQA’s purpose by precluding any ability by the public
or government officials to assess the true nature of the Project’s risks and impacts.
Furthermore, the failure to disclose the characteristics of the crude oil to be processed at
the Refinery infects the air quality analysis and subsequent determination that the crude-by-rail
will cause no significant impacts to Refinery emissions. As only one example, the determination
that any difference in crude feedstocks created by the Project will not cause a significant impact
is based in part on a comparison of API gravity and sulfur content of “various specific crudes
that Valero has purchased in the past three years.” (DEIR Figure 3-8, 3-13). The DEIR
discloses no information regarding the frequency that these. “various” crudes were processed at
the Refinery or how and why these particular crudes were chosen as representative of Refinery
emissions. Without explanation that these particular cnlde feedstocks are an appropriate proxy
for the crude oil to be processed after Proj ect completion, the determination of no significant
impact is not supported by substantial evidence.
37 Laurel Heights Improvement Assn. v. Regents a/University a/California (1988) 47 Ca1.3d
376, 392.A
Page 15
Conclusion
We urge the City of Benicia to revise the Project’s DEIR to address the deficiencies
explained in this letter so that the City Council and general public are provided a full and
accurate accounting of the Project’s environmental impacts.
We appreciate your consideration of these comments.
Sincerely,
SCOTT J. LICHTIG
Deputy Attorney General
For KAMALA D. HARRIS
Attorney General